Stargate Abilene
The flagship of the Stargate program: eight buildings, about 1.2 GW, built for OpenAI by Crusoe and Oracle.
You're looking at a data-center record: a real facility, who runs it, what hardware fills it, and where its power comes from.
Announced at the White House in January 2025, Stargate is the OpenAI, SoftBank, Oracle and MGX program to build AI infrastructure in the US at a stated scale of up to $500B. Its first campus, developed by Crusoe on a Lancium site in Abilene, Texas, comprises eight buildings of about 1.2 GW that Oracle operates for OpenAI. The first GB200 racks arrived in June 2025; in September 2026 Oracle said six buildings, 618 MW, had been delivered. In March 2026 OpenAI dropped plans to expand the site, and Crusoe signed an adjacent 900 MW campus with Microsoft instead.
Specifications & key facts
Each figure is labeled by basis: vendor spec, vendor claim, reported, estimate, or official. "Not publicly disclosed" means exactly that: we never invent values.
Overview
Scale
Power
Cooling
How this connects to the rest of the stack
This record's links at a glance: click a group to jump to it.
Cooling
Hardware deployed
Operated by
Built by
Anchor tenant
Electricity supplied by
Supplied by
Sources
Oracle Q1 FY2027 earnings call transcript (Sep 2026) ↗ · Crusoe: 900 MW Abilene campus for Microsoft (Mar 2026) ↗ · AP: Microsoft takes over Abilene expansion after OpenAI backs away ↗ · Epoch AI: Stargate Abilene (estimates) ↗ · OpenAI Stargate announcement ↗