AI Infrastructure DatabaseThe chips, power and companies behind AI
Saved
Menu
Home How It's Built Watchlist The Stack
Hardware ChipsCompare Chips Servers & SystemsNetworking MemoryFoundries & Packaging Cooling
Facilities Data CentersPower ProjectsCloud & GPU Compute
Intelligence AI ModelsSoftware AI ProductsBenchmarks Research PapersDatasets Concepts
Ecosystem CompaniesStocks PeopleTimeline TrendsFuture of AI
Learn News Ask the Data AI Agents
About About us Methodology Data & API Disclaimer
Options
DATA & API

Free read-only JSON access to the site's cached data.

Dark mode

Guided View
New to chips, data centers and model jargon? We explain key terms as you browse, in plain English. Same data, with the help built in.

Expert View
You already know the stack. Just the data: clean, fast and compact, with no extra explanations. This is the default view.

Interface language
‹ Back
Home › Data Centers › Stargate US sites

Stargate US sites

Data Center AI Campus Under construction Texas, New Mexico, Ohio, Wisconsin, Michigan, US

Six campuses beyond Abilene meant to carry Stargate toward 7 GW.

You're looking at a data-center record: a real facility, who runs it, what hardware fills it, and where its power comes from.

In September and October 2025 OpenAI, Oracle and SoftBank named six US campuses beyond Abilene, which they said would bring Stargate to nearly 7 GW of planned capacity. Oracle leads four, built by developers: Vantage in Shackelford County, Texas (1.4 GW) and Port Washington, Wisconsin (close to 1 GW), STACK's Project Jupiter in Doña Ana County, New Mexico, and Related Digital in Saline Township, Michigan (over 1 GW). SoftBank leads Lordstown, Ohio and Milam County, Texas, where SB Energy is building a 1.2 GW campus. In September 2026 Oracle said none of its four had yet been delivered.

Specifications & key facts

Each figure is labeled by basis: vendor spec, vendor claim, reported, estimate, or official. "Not publicly disclosed" means exactly that: we never invent values.

Overview

Program Stargate: OpenAI, Oracle, SoftBankOfficial
Announced 23 Sep 2025 (five sites); Wisconsin 22 Oct 2025; Michigan 30 Oct 2025Official
Delivery status Oracle: none of Shackelford, New Mexico, Wisconsin or Michigan delivered as of Sep 2026Official Oracle Q1 FY2027 earnings call, 10 Sep 2026

Scale

Program plan Nearly 7 GW incl. Abilene; $400B+ over three yearsOfficial OpenAI, 23 Sep 2025

Sites

Shackelford County, TX Vantage for Oracle/OpenAI; 1.4 GW, 10 buildings, $25B+; not yet delivered (Sep 2026)Official Vantage; Oracle Q1 FY2027 call, 10 Sep 2026
Doña Ana County, NM Project Jupiter: STACK Infrastructure / BorderPlex, Oracle tenant; first building topped out; air permit in progress (Sep 2026)Reported Capacity not stated by OpenAI
Milam County, TX SB Energy builds and operates; OpenAI 1.2 GW lease; SoftBank and OpenAI each invested $500M in SB Energy (Jan 2026)Official
Lordstown, OH SoftBank; with Milam, 'up to 1.5 GW within 18 months' (Sep 2025); no delivery disclosedOfficial
Port Washington, WI Vantage for Oracle/OpenAI; four buildings, close to 1 GW, $15B+; completion 2028Reported
Saline Township, MI Related Digital for Oracle/OpenAI; more than 1 GW, three buildings; delivery targeted end of 2027Reported Construction from ~Mar 2026 after a township lawsuit settlement

How this connects to the rest of the stack

This record's links at a glance: click a group to jump to it.

Operated by

Anchor tenant

Sources

Oracle Q1 FY2027 earnings call transcript (Sep 2026) ↗ · CNBC: Stargate Michigan groundbreaking (Jun 2026) ↗ · OpenAI: Stargate partnership with SB Energy (Jan 2026) ↗ · Epoch AI: where the US Stargate sites stand ↗ · DCD: first Project Jupiter building topped out ↗ · OpenAI: expanding Stargate to Michigan (Oct 2025) ↗ · SiliconANGLE: Stargate Port Washington, Wisconsin (Oct 2025) ↗ · Vantage: Shackelford County campus ↗ · OpenAI: five new Stargate sites (Sep 2025) ↗

Record reviewed as of 2026-11-16; see Methodology.