The most advanced new-reactor site in America, on a retiring coal town.
You're looking at a power record: a real power plant or energy deal — who owns it and which AI buyer it feeds.
TerraPower began non-nuclear construction at Kemmerer, Wyoming in June 2024: a 345 MW sodium-cooled Natrium reactor with molten-salt storage that can flex to 500 MW — sited beside a retiring coal plant to reuse its grid connection and workforce. Target operation ~2030; its NRC review is the pathfinder for advanced-reactor licensing.
Specifications & key facts
Each figure is labeled by basis: vendor spec, vendor claim, reported, estimate, or official. "Not publicly disclosed" means exactly that — we never invent values.
Overview
How this connects to the rest of the stack
This record's links at a glance — click a group to jump to it.
Owned by
Related
Sources