AI Infrastructure DatabaseThe chips, power and companies behind AI
Saved
Menu
Home How It's Built Watchlist The Stack
Hardware ChipsCompare Chips Servers & SystemsNetworking MemoryFoundries & Packaging Cooling
Facilities Data CentersPower ProjectsCloud & GPU Compute
Intelligence AI ModelsSoftware AI ProductsBenchmarks Research PapersDatasets Concepts
Ecosystem CompaniesStocks PeopleTimeline TrendsFuture of AI
Learn News Ask the Data AI Agents
About About us Methodology Data & API Disclaimer
Options
DATA & API

Free read-only JSON access to the site's cached data.

Dark mode

Guided View
New to chips, data centers and model jargon? We explain key terms as you browse, in plain English. Same data, with the help built in.

Expert View
You already know the stack. Just the data: clean, fast and compact, with no extra explanations. This is the default view.

Interface language
‹ Back
Home › Power Projects › TerraPower Natrium (Kemmerer)

TerraPower Natrium (Kemmerer)

Power Project SMR Program Under construction Kemmerer, Wyoming, US

The most advanced new-reactor site in America, on a retiring coal town.

You're looking at a power record: a real power plant or energy deal, who owns it and which AI buyer it feeds.

Kemmerer Unit 1 is TerraPower's first Natrium plant: a 345 MW sodium-cooled fast reactor with molten-salt storage that can flex to 500 MW, sited beside a retiring coal plant to reuse its grid connection and workforce. Non-nuclear work began in June 2024. On 4 March 2026 the NRC voted to grant the first construction permit for a commercial non-light-water reactor, after an 18-month review, and TerraPower started full construction on 23 April 2026 with Bechtel as EPC contractor. Completion is expected in 2030; a separate operating license is still required. In January 2026 Meta agreed to fund two further Natrium units elsewhere.

Specifications & key facts

Each figure is labeled by basis: vendor spec, vendor claim, reported, estimate, or official. "Not publicly disclosed" means exactly that: we never invent values.

Overview

Developer TerraPower (founded by Bill Gates); licensee US SFR OwnerOfficial
Capacity 345 MW base / 500 MW with storage boostOfficial
Construction start June 2024 (non-nuclear scope); full construction 23 Apr 2026Official TerraPower, 23 Apr 2026
EPC contractor BechtelOfficial TerraPower, Apr 2026

Regulatory

NRC construction permit Commission vote 4 Mar 2026; CPAR-1 issued 9 Mar 2026; review took 18 months vs 27 scheduledOfficial TerraPower, Mar 2026; Federal Register 2026-05067
Operating license Separate NRC application still requiredReported ANS, Mar 2026

Schedule

Completion target 2030Official TerraPower, Mar 2026 (DOE Advanced Reactor Demonstration Program)

Related deal

Meta agreement Funds two new Natrium units (up to 690 MW, as early as 2032) plus rights to six more (2.1 GW by 2035); site to be identifiedReported World Nuclear News, 9 Jan 2026

How this connects to the rest of the stack

Owned by · 1 Related · 3 TerraPower Natrium (Kemmerer)

This record's links at a glance: click a group to jump to it.

Owned by

Sources

TerraPower: construction begins on Kemmerer Unit 1 (Apr 2026) ↗ · TerraPower: NRC approves Natrium construction permit (Mar 2026) ↗ · WNN: Meta announces agreements for new nuclear (Jan 2026) ↗ · TerraPower Natrium ↗