Vogtle Units 3 & 4
电力项目
新建核电
运营中
Waynesboro, Georgia, US
America's newest reactors — the hard-won template for building big again.
您正在查看一条电力记录:一个真实的发电站或能源协议——谁拥有它,它为哪家 AI 买家供电。
照片: NRC · Public domain · Wikimedia Commons
Vogtle 3 (2023) and 4 (2024) were the first new US reactors in a generation: two AP1000s adding ~2,234 MW, seven years late and roughly double the original budget — the cautionary cost story every AI-driven nuclear conversation must answer, and also proof the US can still complete them. Georgia's data-center boom is already absorbing the output.
规格与关键参数
每个数据均标注来源依据:厂商规格、厂商声明、公开报道、估算或官方数据。"未公开披露"即字面含义——我们从不捏造数值。
Overview
Owner
Georgia Power (Southern Company) and partnersOfficial
Capacity
~2,234 MW across Units 3–4Official
In service
Unit 3 July 2023; Unit 4 April 2024Official
Technology
Westinghouse AP1000Official