AI Infrastructure DatabaseThe chips, power and companies behind AI
Saved
Menu
Home How It's Built Watchlist The Stack
Hardware ChipsCompare Chips Servers & SystemsNetworking MemoryFoundries & Packaging Cooling
Facilities Data CentersPower ProjectsCloud & GPU Compute
Intelligence AI ModelsSoftware AI ProductsBenchmarks Research PapersDatasets Concepts
Ecosystem CompaniesStocks PeopleTimeline TrendsFuture of AI
Learn News Ask the Data AI Agents
About About us Methodology Data & API Disclaimer
Options
DATA & API

Free read-only JSON access to the site's cached data.

Dark mode

Guided View
New to chips, data centers and model jargon? We explain key terms as you browse, in plain English. Same data, with the help built in.

Expert View
You already know the stack. Just the data: clean, fast and compact, with no extra explanations. This is the default view.

Interface language
‹ Back
Home › Power Projects › Duane Arnold Energy Center

Duane Arnold Energy Center

Power Project Nuclear Restart Restart planned; target Q1 2029 Palo, Iowa, US

Iowa's shut reactor, restarting for Google around early 2029.

You're looking at a power record: a real power plant or energy deal, who owns it and which AI buyer it feeds.

Photo: Jssteinke · Public domain · Wikimedia Commons

NextEra's 615 MW Duane Arnold plant, Iowa's only nuclear station, closed in 2020 after derecho storm damage to its cooling towers. In October 2025 NextEra and Google announced a 25-year power purchase agreement to support a restart targeted for the first quarter of 2029, and NextEra agreed to buy the 30% held by two cooperatives to become sole owner. On 8 September 2026 the DOE closed a loan of up to $1.9B for the restart. NRC licensing approvals were still pending as of that date.

Specifications & key facts

Each figure is labeled by basis: vendor spec, vendor claim, reported, estimate, or official. "Not publicly disclosed" means exactly that: we never invent values.

Overview

Owner NextEra Energy (moving to 100% after buying CIPCO and Corn Belt Power's combined 30%)Official NextEra-Google announcement, 27 Oct 2025
Capacity 615 MWOfficial DOE, Sep 2026
Offtaker Google: 25-year PPA; CIPCO buys the remaining output on the same termsReported World Nuclear News, Oct 2025
Shutdown 2020, after August 2020 derecho damaged cooling towersOfficial
Restart target First quarter 2029, subject to approvalsOfficial NextEra, 27 Oct 2025

Finance

DOE loan Up to $1.9B, closed 8 Sep 2026 (Office of Energy Dominance Financing)Official DOE release, 8 Sep 2026

Regulatory

NRC Restart licensing approvals pending; licensing requests filed from January 2025Official DOE release, Sep 2026; ANS, 2025-26

How this connects to the rest of the stack

This record's links at a glance: click a group to jump to it.

Supplier to

Owned by

Sources

DOE: loan closed to restart Duane Arnold (Sep 2026) ↗ · WNN: Duane Arnold restart underpins NextEra-Google collaboration (Oct 2025) ↗ · NextEra ↗

Record reviewed as of 2026-11-16; see Methodology.