Duane Arnold Energy Center
Iowa's shut reactor, restarting for Google around early 2029.
You're looking at a power record: a real power plant or energy deal, who owns it and which AI buyer it feeds.
Photo: Jssteinke · Public domain · Wikimedia Commons
NextEra's 615 MW Duane Arnold plant, Iowa's only nuclear station, closed in 2020 after derecho storm damage to its cooling towers. In October 2025 NextEra and Google announced a 25-year power purchase agreement to support a restart targeted for the first quarter of 2029, and NextEra agreed to buy the 30% held by two cooperatives to become sole owner. On 8 September 2026 the DOE closed a loan of up to $1.9B for the restart. NRC licensing approvals were still pending as of that date.
Specifications & key facts
Each figure is labeled by basis: vendor spec, vendor claim, reported, estimate, or official. "Not publicly disclosed" means exactly that: we never invent values.
Overview
Finance
Regulatory
How this connects to the rest of the stack
This record's links at a glance: click a group to jump to it.
Supplier to
Owned by
Related
Sources
DOE: loan closed to restart Duane Arnold (Sep 2026) ↗ · WNN: Duane Arnold restart underpins NextEra-Google collaboration (Oct 2025) ↗ · NextEra ↗
Record reviewed as of 2026-11-16; see Methodology.