AI Infrastructure DatabaseThe chips, power and companies behind AI
Saved
Menu
Home How It's Built Watchlist The Stack
Hardware ChipsCompare Chips Servers & SystemsNetworking MemoryFoundries & Packaging Cooling
Facilities Data CentersPower ProjectsCloud & GPU Compute
Intelligence AI ModelsSoftware AI ProductsBenchmarks Research PapersDatasets Concepts
Ecosystem CompaniesStocks PeopleTimeline TrendsFuture of AI
Learn News Ask the Data AI Agents
About About us Methodology Data & API Disclaimer
Options
DATA & API

Free read-only JSON access to the site's cached data.

Dark mode

Guided View
New to chips, data centers and model jargon? We explain key terms as you browse, in plain English. Same data, with the help built in.

Expert View
You already know the stack. Just the data: clean, fast and compact, with no extra explanations. This is the default view.

Interface language
‹ Back
Home › Data Centers › xAI Colossus

xAI Colossus

Data Center AI Campus Operating (capacity leased to Anthropic) Memphis, Tennessee, US

100,000 GPUs in 122 days: the build that reset the industry's clock.

You're looking at a data-center record: a real facility, who runs it, what hardware fills it, and where its power comes from.

xAI converted a former Electrolux appliance factory in Memphis into its first AI supercomputer: roughly 100,000 H100-class GPUs brought online in 122 days in 2024, later expanded to more than 220,000 NVIDIA GPUs (H100, H200 and GB200) on Spectrum-X Ethernet. On-site gas turbines bridged the grid gap; Shelby County permitted 15 of them in July 2025 after challenges from local groups. Grok 3 and 4 were trained here. After SpaceX acquired xAI in February 2026, the company agreed in May 2026 to lease all of Colossus 1, more than 300 MW, to Anthropic.

Specifications & key facts

Each figure is labeled by basis: vendor spec, vendor claim, reported, estimate, or official. "Not publicly disclosed" means exactly that: we never invent values.

Overview

Operator xAI, a SpaceX subsidiary since Feb 2026 (styled SpaceXSI on its own pages)Official
First online September 2024 (122-day build)Reported
Tenant Anthropic: all compute capacity, from May 2026Official Commercial terms not disclosed in the announcements
Notable Trained Grok 3 and Grok 4Official

Scale

GPUs ~100,000 at launch; 220,000+ (H100, H200, GB200) by May 2026Official SpaceXSI, 6 May 2026
Power 300+ MWOfficial Anthropic announcement, 6 May 2026

Power

Supply MLGW/TVA grid + on-site gas turbines + Tesla Megapack bufferingReported
Air permit 15 gas turbines permitted by Shelby County Health Dept (Jul 2025); appeal dismissed as moot (Dec 2025)Reported

How this connects to the rest of the stack

This record's links at a glance: click a group to jump to it.

Interconnect & networking

Operated by

xAI

Anchor tenant

Sources

Anthropic: compute agreement for Colossus 1 (May 2026) ↗ · SpaceXSI: Anthropic compute partnership (May 2026) ↗ · CNN: SpaceX is acquiring xAI (Feb 2026) ↗ · Tennessee Lookout: appeal of xAI turbine permits (Jul 2025) ↗ · NVIDIA on Colossus/Spectrum-X ↗

Record reviewed as of 2026-11-16; see Methodology.