xAI Colossus
100,000 GPUs in 122 days: the build that reset the industry's clock.
You're looking at a data-center record: a real facility, who runs it, what hardware fills it, and where its power comes from.
xAI converted a former Electrolux appliance factory in Memphis into its first AI supercomputer: roughly 100,000 H100-class GPUs brought online in 122 days in 2024, later expanded to more than 220,000 NVIDIA GPUs (H100, H200 and GB200) on Spectrum-X Ethernet. On-site gas turbines bridged the grid gap; Shelby County permitted 15 of them in July 2025 after challenges from local groups. Grok 3 and 4 were trained here. After SpaceX acquired xAI in February 2026, the company agreed in May 2026 to lease all of Colossus 1, more than 300 MW, to Anthropic.
Specifications & key facts
Each figure is labeled by basis: vendor spec, vendor claim, reported, estimate, or official. "Not publicly disclosed" means exactly that: we never invent values.
Overview
Scale
Power
How this connects to the rest of the stack
This record's links at a glance: click a group to jump to it.
Interconnect & networking
Cooling
Hardware deployed
Operated by
Built by
Anchor tenant
Related
Sources
Anthropic: compute agreement for Colossus 1 (May 2026) ↗ · SpaceXSI: Anthropic compute partnership (May 2026) ↗ · CNN: SpaceX is acquiring xAI (Feb 2026) ↗ · Tennessee Lookout: appeal of xAI turbine permits (Jul 2025) ↗ · NVIDIA on Colossus/Spectrum-X ↗