AI Infrastructure DatabaseThe chips, power and companies behind AI
Saved
Menu
Home How It's Built Watchlist The Stack
Hardware ChipsCompare Chips Servers & SystemsNetworking MemoryFoundries & Packaging Cooling
Facilities Data CentersPower ProjectsCloud & GPU Compute
Intelligence AI ModelsSoftware AI ProductsBenchmarks Research PapersDatasets Concepts
Ecosystem CompaniesStocks PeopleTimeline TrendsFuture of AI
Learn News Ask the Data AI Agents
About About us Methodology Data & API Disclaimer
Options
DATA & API

Free read-only JSON access to the site's cached data.

Dark mode

Guided View
New to chips, data centers and model jargon? We explain key terms as you browse, in plain English. Same data, with the help built in.

Expert View
You already know the stack. Just the data: clean, fast and compact, with no extra explanations. This is the default view.

Interface language
‹ Back
Home › Data Centers › Meta Hyperion

Meta Hyperion

Data Center AI Campus Under construction Richland Parish, Louisiana, US

A campus the size of Manhattan: 5 GW and $50B+ in rural Louisiana.

You're looking at a data-center record: a real facility, who runs it, what hardware fills it, and where its power comes from.

Hyperion is Meta's AI campus in Richland Parish, Louisiana, under construction since December 2024. Announced at about 2 GW and $10B, it was expanded in July 2026 to 5 GW of compute capacity and more than $50B of investment; Meta expects about 2 GW by 2030 and the full campus around 2032. Entergy Louisiana won approval in 2025 for three new gas plants to serve it, and in March 2026 proposed seven more, totaling over 5,200 MW, plus about 240 miles of 500 kV transmission, still pending regulatory approval.

Specifications & key facts

Each figure is labeled by basis: vendor spec, vendor claim, reported, estimate, or official. "Not publicly disclosed" means exactly that: we never invent values.

Overview

Operator Meta
Investment $50B+ (Jul 2026); was $10B (2024) and $27B (Oct 2025)Official Earlier figures per Meta spokesperson to CNBC, Jul 2026
Timeline ~2 GW by 2030; full build ~2032Reported Meta spokesperson to CNBC, Jul 2026
Financing Blue Owl-managed JV (Beignet Investors); Meta minority partner and tenantReported

Scale

Announced scale ~2 GW initially; expanded to 5 GW (Jul 2026)Official

Power

Supply Entergy Louisiana: 3 CCGTs approved Aug 2025; 7 more (5,200+ MW) + ~240 mi of 500 kV lines proposed Mar 2026, pending LPSCOfficial

How this connects to the rest of the stack

This record's links at a glance: click a group to jump to it.

Operated by

Electricity supplied by

Related

Sources

Meta: Louisiana data center expansion (Jul 2026) ↗ · Entergy Louisiana: new Meta agreement (Mar 2026) ↗ · CNBC: Hyperion investment reaches $50B (Jul 2026) ↗ · Entergy Louisiana: LPSC approval (Aug 2025) ↗ · Entergy on the Richland Parish project ↗

Record reviewed as of 2026-11-16; see Methodology.