{"data":{"slug":"susquehanna","etype":"power","name":"Susquehanna Steam Electric Station","cat":"Nuclear Supply Deal","subtitle":"The reactor with a data center at the fence line: AWS's landmark arrangement.","summary":"Talen's 2.5 GW Susquehanna plant hosts the data campus Amazon bought in 2024, originally served behind the meter under an interconnection change FERC rejected in November 2024. In June 2025 Talen and AWS replaced it with a 17-year, ~$18B front-of-meter retail PPA for up to 1,920 MW through 2042, ramping to 840-1,200 MW by 2029 and 1,680-1,920 MW by 2032 depending on AWS's build pace. The switch from the 300 MW behind-the-meter setup was planned for the spring 2026 refueling outage. The parties are also studying uprates and small modular reactors.","attrs":[{"b":"Official","g":"Overview","l":"Owner","v":"Talen Energy"},{"b":"Official","g":"Overview","l":"Plant capacity","u":"MW","v":"~2,500"},{"b":"Official","g":"Overview","l":"AWS arrangement","n":"Talen, Jun 2025","v":"Up to 1,920 MW through 2042, front-of-meter retail PPA (signed 11 Jun 2025)"},{"b":"Reported","g":"Overview","l":"Contract value","n":"POWER Magazine, 12 Jun 2025","v":"~$18B over 17 years"},{"b":"Official","g":"Schedule","l":"Delivery ramp","n":"Talen, Jun 2025, via POWER Magazine","v":"840-1,200 MW by 2029; 1,680-1,920 MW by 2032"},{"b":"Official","g":"Schedule","l":"Front-of-meter transition","n":"Talen, Jun 2025; completion not confirmed in a primary source reviewed","v":"Planned during spring 2026 refueling outage; prior behind-the-meter supply 300 MW"},{"b":"Official","g":"Overview","l":"Further options","n":"Talen, Jun 2025","v":"Joint evaluation of plant uprates and SMRs at Talen's Pennsylvania sites; no commitments"},{"b":"Official","g":"Overview","l":"Regulatory note","v":"Original behind-the-meter ISA amendment rejected by FERC (Nov 2024); restructured front-of-meter"}],"kf":{"type":"Nuclear PPA + campus","buyer":"Amazon (AWS)","status":"Ramping; full volume by 2032","capacity":"up to 1,920 MW to AWS"},"aliases":["Susquehanna AWS","Cumulus campus"],"ticker":null,"exchange":null,"hq":null,"founded":null,"website":null,"status":"Operating","region":"Salem Township, Pennsylvania, US","asof":"2026-11-16","sources":[{"url":"https://www.powermag.com/talen-amazon-launch-18b-nuclear-ppa-a-grid-connected-ipp-model-for-the-data-center-era/","label":"POWER: Talen, Amazon launch $18B nuclear PPA (Jun 2025)"},{"url":"https://www.talenenergy.com/talen-energy-and-aws-sign-nuclear-energy-agreement-to-power-the-future/","label":"Talen-AWS expansion"}]},"meta":{"found":true,"count":1,"served_from":"site cache (no live upstream calls)","as_of":"2026-11-28T08:25:07+00:00","disclaimer":"Research and information only, not investment advice. Structured records carry basis labels (vendor spec / reported / estimate); market quotes are delayed/indicative.","attribution":"Records compiled from vendor documentation, official filings and reputable public reporting; market quotes via financial data providers. See /data-sources."}}